Completed Projects

At Bhupal Infra, we take pride in delivering high-quality transmission infrastructure that powers progress. With a commitment to excellence and innovation, we have successfully completed 7 major transmission projects to date. These projects stand as a testament to our expertise in design, engineering, erection, testing, and commissioning of critical power transmission networks.

Project DescriptionClient
Supply,Erection,testing of 132 KV DC/SC line from 220/132 KV SS Yeddumailaram to 132/33 KV SS Pashamailaram with connected baysTS TRANSCO
Supply, Erection, testing of 132KV DC line from Existing 132/33KV SS at Rayachoti to the Proposed 132/33KV SS at T.Sundupalli in Kadapa District for
P Chandra Reddy& Co as Sub-Contractor
AP TRANSCO
765 KV D/C Hyderabad Kurnool line (Nandikotkur) (40 KMS) for KEC as Sub-ContractorESSEL
Balance Civil and Erection works for 400KV Quad Moose DC line Nandiwanaparthy to Shankarpally 400KV (37 kms) for Gurupreet as Sub-ContractorTS TRANSCO
Supply , Erection, Testing& Commissioning of 220KV DC line(36 KM) from 400/220/132 KV SS Gajwel to 220/132/33KV SS Siddipet and connected bays at both ends (total 4 nos. 220 KV Bays) in Siddipet District on turnkey basis for Gurupreet as Sub-ContractorTS TRANSCO
Supply , Erection, testing and commissioning of (i) 220/132KV SS Banswada with Substation Automation System (2x100 MVA PTRs) (ii) 220 KV DC line (76 KM) from 400/220 KV SS Dichpally to proposed 220/132KV SS Banswada and (iii) 2Nos. 220KV Bays at 400/220kV Sub-station at Dichpally in Nizamabad District on turnkey basis for Gurupreet as Sub-Contractor.TS TRANSCO
132 KV LILO line from existing (i) Sadasivpet-Singore 132 kV line (4.6 Km) along with 2 nos. 132 KV Bays. (ii) Sadasivpet-Zaheerabad 132 KV line (2.0 Km) along with 2 nos. 132 KV BaysTS TRANSCO

Ongoing Projects

Project DescriptionClient
Supply, Erection,laying & testing of 220KV and 132KV diversion , shifting of OH line with UG cable Shivarampally-Gachibowli.TS TRANSCO (RR CORP)